Ontinyent awards contract for athletics track lighting renovation

The Ontinyent City Council has awarded a contract for the renovation of the lighting at the municipal athletics track to IMESAPI SL for €239,293.48, funded by the Valencia Provincial Council.

Ontinyent awards contract for athletics track lighting renovation

The Ontinyent City Council has announced the awarding of a contract for the renovation and electrical adaptation of the lighting at the municipal athletics track. The Contracting Committee has selected the national company IMESAPI SL, based in the Valencia region, for a total of €239,293.48. This project is financed through the Valencia Provincial Council's Open Investment Plan.

The renovation will not only replace the existing lighting system but will also include various improvements, such as the supply and installation of new luminaires with columns in the southeast curve and the eastern access side of the sports complex.

Ontinyent's mayor, Jorge Rodríguez, emphasised that this contract award represents a significant step towards improving sports facilities, particularly the athletics track, enhancing conditions for athletes and users while significantly reducing energy consumption.

Natàlia Enguix, the Vice President of the Valencia Provincial Council and first deputy mayor of Ontinyent, noted that the municipality is maximising the benefits of the Open Investment Plan, which has allocated €2.8 million. This includes nearly €300,000 for children's areas, €2.2 million for the renovation of Plaza de la Concepción, and now this project, which exceeds €240,000. Enguix stated, "This is also a testament to what we aimed to achieve with the Open Investment Plan—investments that benefit the entire community."

Ferran Gandia, the councillor for sports, highlighted that this project addresses a long-awaited reform that has been highly requested by athletes and clubs using the track. He added, "Thanks to the investment commitment from the Provincial Council, particularly the efforts of Natàlia Enguix, Ontinyent has secured significant funding to continue improving its sports facilities."

The project involves replacing the current lighting system, which uses discharge projectors, with a new installation consisting of 61 LED projectors distributed across the six existing towers and the video finish area. This upgrade will provide more uniform and efficient lighting suitable for both training and competitions.

Another key aspect of the project is the reduction in energy consumption, with the installed power decreasing from approximately 100 kW to 60.30 kW, representing a reduction of about 40% compared to the current situation, exceeding the initial target of 35%. The new infrastructure will also incorporate an intelligent control system that will allow for the regulation of light intensity according to the needs of each activity, further optimising energy consumption and avoiding operating at maximum power at all times.

In addition to the projector replacement, the project includes a comprehensive upgrade of the electrical installation, renewing lines, control panels, and protections, as well as reviewing the structural elements supporting the lighting towers. The works will also enhance lighting in various pedestrian areas around the track to improve usability and accessibility to the facilities.

IMESAPI SL, the company awarded the contract, has extensive experience in lighting sports facilities. Notable projects include the replacement of luminaires at the athletics track, football field, throwing area, and hockey pitch at the High-Performance Centre in Madrid, as well as lighting for the athletics track at the Gran Canaria Sports City and the Insular Athletics Centre in Tenerife. In the Valencia region, IMESAPI has also modernised the lighting at the athletics track in Castellón.